We have finally got though the bricking on 14/9 after 5 weeks and things are starting to move along nicely again! It is obvious that brickies are in short supply and a major speed inhibitor when spread across many jobs.

Since the bricking finished we have had gutters and fascias installed, the top roof tiles laid, and the front balcony pillars/piers rendered today.

We are very happy with how everything is looking and the Barramundi Monier Horizon tiles with A-line ridging look superb! The rendering guys have done a great job and seem like a genuine & hard working team!

Next I guess we will see the internal electrical start to get roughed in, upper bricks cleaned, and the lower roof get installed once the scaffolding goes.


Fascia & Guttering done 17/9
Top Roof tiles complete 24/9



Front rendering complete 28/9