Since then we have had mostly 3/4 people onsite at any time with many days/weeks where they were at other worksites.
The scaffolding went up in one day on 31/8 during a 2.5 week relocation to other jobs for the brickies.
The ground level bricks were completed on 7/9.
The 11/9 was the end of the 20th week of the 40 week contract period and although our SS says they are looking to accelerate, I am concerned with our progress given the trades are juggling many jobs.
We have been told the bricking would be finished by 11/9, Scaffold lifted for Fascia 16/9, Fascia 17/9, and Top roof tiles starting 18/9
We are loving the look of the bricks on the house! We just wish things were quicker!
A picture timeline is below:-
12/9 |
12/9 |
12/9 |
7/9 - Ground-level bricks are complete |
7/9 |
31/8 |
19/8 |
19/8 |
19/8 |
17/8 |
15/8 |
15/8 |
15/8 |
13/8 |
13/8 |
12/8 |
12/8 |