Friday 15 May 2015

Internal drainage, Formwork & Steel installed

Some serious progress has been made this week... The concretors have been doing a exceptional job! Provincial use a firm called Solid Concrete with Tony and team. We believe the slab will be poured next Wednesday.

Over the past week the following has been done:-
  • The ground has been prepared and edge formwork constructed.
  • The under-slab drainage installed
  • Laying the plastic sheeting concrete underlay
  • Fix reinforcement in the beams using steel mesh at the bottom
  • Fix reinforcement in the slabs using steel mesh at the top
Next steps if my research is correct are:-
  • Termite Barrier Installed?
  • Pour and compact the concrete
  • Finish slab surface
  • Cure the slab 



No comments:

Post a Comment